Lane closures on SR-69 in Jasper are delayed until Wednesday, May 1. The closures are part of ongoing improvements in the area.
Lane closures on SR-69 in Jasper delayed to May 1
Apr 29
Region/County | West Central/Walker |
Type of Work | Bridge Replacement |
Route | SR-5, SR-195, SR-69, US-78A |
Projected Start | January 17, 2024 |
Projected Completion | Spring 2025 |
Traffic Impact | Bridge closure |
The Alabama Department of Transportation plans to replace the bridge and make intersection improvements on SR-5 over the SR-69 underpass in Jasper.
The project is expected to begin Wednesday, January 17 with the bridge demolition, which will occur for about two weeks. Construction will then take place for approximately one year, weather permitting. The intersection…