Resurfacing on I-65 from the 16th Street overpass to Daniel Payne Drive

Concrete pavement rehab and resurfacing on I-65 from 16th Street North overpass to Daniel Payne Drive

Region/County East Central/Jefferson
Type of WorkResurfacing
RouteI-65
Projected StartDecember 8, 2023
Projected CompletionSummer 2024
Project NumberIMI065535100073403
Project Cost$8,260,886.61
Funding Source$7,434,797.95 Federal and $826,088.66 State
Project StatusActive