I-565 Advanced Corridor Management

This intelligent transportation system project on I-565 from Mooresville Road in Limestone County to U.S. 72 in Huntsville will add 10 traffic cameras, three dynamic message systems, and two weather stations for monitoring conditions and aiding traffic flow on the corridor.

Region/County North/Limestone, Madison
Type of WorkTransportation Systems Management and Operations
RouteI-565
Projected StartJuly 2023
Projected CompletionFall 2024
Traffic ImpactLane closures or traffic stoppages possible at times for installation of poles or structures for cameras and message boards
Project NumberCRPIM-I565(320)
Project Cost$5,195,555.00
Project StatusActive
Get the latest traffic information at algotraffic.com or on the ALGO Traffic app.
Related Posts
Uprights for the overhead sign structures that will support the message boards on I-565 westbound between County Line Road and Greenbrier Road.

Updated timeline: I-565 overhead message board schedule changes

Motorists will soon benefit from travel information displayed on overhead message boards on I-565 in Limestone and Madison counties.

A contractor will install the dynamic message signs (DMS) at three locations as part of the ongoing $5.2 million advanced corridor management project. The project, which began in…

Read More “Overhead message boards coming to I-565”

Workers install a concrete pole on I-565 near Mooresville Road in Limestone County for a future traffic camera on Tuesday.

Poles for the first Alabama Department of Transportation traffic cameras on I-565 in Huntsville and Madison will go up this week.

Weather permitting, contractors will install the concrete poles at eight sites in Limestone and Madison counties over the course of three days — Tuesday, March 19, through Thursday, March 21. Lane closures on I-565…