Contractor to pour bridge deck in Jasper

Aerial view of the SR-5 bridge under construction in Jasper with the sun rising in the background
Work continues on the SR-5 bridge in Jasper.
Apr 29

The Alabama Department of Transportation has approved lane closures to allow the contractor to pour the bridge deck on SR-5 over SR-69 (US-78A) in Jasper on Tuesday, April 30, weather permitting.

The contractor plans to close the SR-69 outside lanes from 5 a.m. until later in the afternoon.

The work is part of the ongoing bridge replacement and intersection improvement project that is intended to improve safety, mobility and commerce. The project is expected to be completed by the end of the year.

Wright Brothers Construction Company was awarded the project at $8.8 million.

Visit ALGOTraffic.com for up-to-date traffic information and ALDOTNews.com to learn more about this project and others around the state.

Related Project
Region/County West Central/Walker
Type of WorkBridge Replacement
RouteSR-5, SR-195, SR-69, US-78A
Projected StartJanuary 17, 2024
Projected CompletionSpring 2025
Traffic ImpactBridge closure

The Alabama Department of Transportation plans to replace the bridge and make intersection improvements on SR-5 over the SR-69 underpass in Jasper.

The project is expected to begin Wednesday, January 17 with the bridge demolition, which will occur for about two weeks. Construction will then take place for approximately one year, weather permitting. The intersection…