ALDOT to install safety improvements (traffic lighting installation) on I-20/59 at the Exit 79 interchange southeast of Cottondale to include the on and off ramps.
| Region/County | West Central/Tuscaloosa |
| Type of Work | Traffic Lighting |
| Route | I-20/59 |
| Projected Start | November 2024 |
| Projected Completion | Summer 2025 |
| Traffic Impact | Possible shoulder closures |
| Project Number | HSIP-I059(414) |
| Project Cost | $1,635,813.00 |
| Project Status | Completed |