The Alabama Department of Transportation (ALDOT) plans to resurface two roads in Clanton to improve safety and mobility.
The nighttime project includes resurfacing a portion of US-31, from the intersection of Newport Avenue to Inverness Drive, as well as a segment of SR-145, stretching from US-31 to First Street.
Work is scheduled to begin Monday, May 19 and will continue until fall 2025, weather permitting. No lane closures are allowed from 7 a.m. until 8 p.m. to reduce the impact on traffic.
Wiregrass Construction Company was awarded the project at $2.04 million.
Motorists should expect possible delays and are encouraged to observe work-zone speed limits.
For real-time traffic updates and more, download the ALGOTraffic app or visit ALGOTraffic.com.
| Region/County | West Central/Chilton |
| Type of Work | Resurfacing and traffic signal upgrades |
| Route | US-31 and SR-145 |
| Projected Start | May 19, 2025 |
| Projected Completion | Fall 2025 |
| Project Number | STPAA-HSIP-MR25(900) |
| Project Cost | $2,040,000.00 |
| Project Status | Active |