This project is constructing additional lanes, turn lanes, intersection improvements, and interchange ramp modifications, including grading, drainage, pavement, bridge removal, bridges, bridge culvert, traffic stripe, and traffic signals on SR-304 (Old CR-24) from west of US-31 at Tanner to east of the I-65 Exit 347 interchange in Athens. The eastbound lanes have been constructed and are now carrying traffic (one lane in each direction) while the original, two-lane road undergoes removal and reconstruction to become the future westbound lanes.
Region/County | North/Limestone |
Type of Work | Additional lanes/bridge construction |
Route | SR-304 |
Projected Start | August 2021 |
Projected Completion | Spring 2025 |
Traffic Impact | Expect lane shifts and be prepared to merge near the U.S. 31 intersection and I-65 interchange. |
Project Number | RAED-042-888-035 |
Project Cost | $13,306,739.00 |
Project Status | Active |