This project will construct additional lanes, including grading, drainage, and widening of two bridges, on about five miles of I-565 from west of the County Line Road interchange to east of Wall Triana Highway in Madison. The project includes resurfacing and traffic stripe.

Region/County North/Limestone, Madison
Type of WorkAdditional lanes/bridge widening
RouteI-565
Projected StartSeptember 2024
Projected CompletionFall 2026
Traffic ImpactMedian and shoulder restricted by concrete barriers. Travel lanes may be narrower. Nighttime lane closures possible.
Project NumberRACRNH-RACRIM-I565 (315)
Project Cost$28,992,350.52
Project StatusActive
Get the latest traffic information at algotraffic.com or on the ALGO Traffic app.
Related Posts
Signs for the project are in place, including this work zone sign near Exit 7 (County Line Road), at the west end of the project on the eastbound roadway.

The contractor on the I-565 widening project anticipates starting work next week to expand the interstate spur to six lanes through Madison.

The $29 million project stretches from west of County Line Road to east of Wall Triana Highway. It includes adding a third lane on each roadway and widening two sets of bridges —…