Pavement rehabilitation on I-65 from Raleigh Avenue Overpass to a pavement joint 0.5 mile south of University Boulevard
| Region/County | East Central/Jefferson |
| Type of Work | Pavement rehabilitation |
| Route | I-65 |
| Projected Start | April 28, 2023 |
| Projected Completion | Summer 2024 |
| Project Number | IM IO65 534 100069281 |
| Project Cost | $6,805,389.55 |
| Funding Source | $6,124,850.59 in federal funds, and $680,538.96 in state funds |
| Project Status | Completed |